PG&E To Charge Ratepayers For More Than Half of $2.2 Billion Pipeline Project

The approval angered officials from San Bruno, where a pipeline explosion killed eight people in 2010.

-By Bay City News-

The California Public Utilities Commission today approved a plan that will allow PG&E to charge ratepayers for more than half of a $2.2 billion project to upgrade its natural gas pipelines.

The approval of the plan, with a last-minute change removing a requirement that the utility take lower profits for five years, angered officials from San Bruno where a ruptured pipeline resulted in an explosion that killed eight people and destroyed 38 homes in 2010.

PG&E's project includes pressure testing 783 miles of natural gas pipelines, replacing 186 miles of pipelines while upgrading another 199 miles and installing 228 automatic shutoff valves.

The plan approved by the CPUC at its meeting in San Francisco Thursday requires PG&E ratepayers to foot the bill for roughly 55 percent of the projects while the utility's shareholders will fund the rest.

An initial ruling had initially put ratepayers on the hook for roughly 49 percent of the project and initially included a five-year term in which PG&E's rate of profit on its improvement investments would be reduced to 6.05 percent as part of a judge's recommendation.

But Wednesday evening, regulators amended the plan to disallow that recommendation and raise the rate to about 11 percent, giving what San
Bruno Mayor Jim Ruane said equated to a $130 million "Christmas present" to
PG&E.

"It's a slap in the face," Ruane said. "They blew up our town, they killed eight people, and here we are giving them cash."

State Sen. Jerry Hill, D-San Mateo, said the change showed that "PG&E owns the state of California and the PUC."

Hill said, "It's shameful that they would allow PG&E to profit from their behavior, their negligence, their poor maintenance."

Thomas Long, legal director for the watchdog group The Utility Reform Network, said many of the pipelines in the project are only being replaced because PG&E lost the records for them.

"They had no idea if these pipelines were operating at safe pressures," Long said. "PG&E loses records, we should pay for it?"

PG&E spokeswoman Brittany Chord said the utility's shareholders have already spent $1.5 billion since 2010 on work to meet previously existing regulations and that "this proposed plan was put forward to address new safety expectations that were set by the CPUC."

Chord said, "We know we made a lot of mistakes, and we know we have a lot of work to do."

She said PG&E had sought to have ratepayers fund a higher percentage of the pipeline project -- which is expected to add about $2 to the average monthly residential utility bill -- but they were rebuffed by the CPUC.

In announcing the commission's decision, Commissioner Mike Florio said the project was "about moving forward and creating the safest natural gas infrastructure in the nation."

Florio said the ruling was a balance between the requests of PG&E and those of San Bruno officials and survivors of the blast.

"We have to make sure PG&E isn't rewarded for the past ... but we can't expect PG&E in the past to meet standards that didn't exist until now," he said.


Copyright © 2012 by Bay City News, Inc. -- Republication, Rebroadcast or any other Reuse without the express written consent of Bay City News, Inc. is prohibited.

What do you think? Should ratepayers be asked to help pay for the upgrades to the gas transmission lines?  Tell us in comments.

 

Don’t be left out of the conversation taking place in Belmont--Sign up for our daily newsletter|Like Belmont|Patch on Facebook | Follow us on Twitter | Start your own blog

Don’t be left out of the conversation taking place in San Carlos--Sign up for our daily newsletter | Like us on Facebook | Follow us on Twitter| Start a blog


Newsletter & Alerts

Get the best stories each day and important breaking news

Subscribe

Not from Belmont Patch? Find your Local Patch »

Note Article
Just a short thought to get the word out quickly about anything in your neighborhood.
Share something with your neighbors. Write a new post... What's up? Make an announcement, speak your mind, or sell something
Michele Moyer June 16, 2013 at 09:17 am
Thanks Joan - there is one in the sub-head of the blog I posted on School-Force Voices today; wouldRead More love if it could be corrected. Been scratching my head til I saw this post :)
Joan S. Dentler (Editor) June 16, 2013 at 11:20 am
Sorry about that! There's nothing I can do on my end----it's system-wide bug, which I believe isRead More fixed now. :)
Belmont96 June 13, 2013 at 09:40 am
I also preferred the 'old' Patch - this format makes it difficult to find articles that are aren'tRead More that old. One example was the informative article on who was running for city Council. I was having problems finding it and finally had to query on a candidate's name to find. I don't recall having that issue with the original format. Also our neighborhood had a water break line and we were without water for some hours a few Sundays ago. I tried to find out the reason for the break (because of construction or old pipes?) and could not find anything on the Patch regarding this. Not sure if they just didn't report or I just couldn't find.
Judi June 14, 2013 at 07:28 am
Not crazy about the new Patch either. Also, I want to post-for sale, and this section is crowdedRead More with announcements, etc.
Pearl June 14, 2013 at 04:15 pm
Another thing that needs to be fixed: When you go to leave a comment, it takes you over to whereRead More you have to sign in, you sign in expecting to be returned to the article on which you are commenting, but it, instead, takes you back to some different article. PLEASE FIX THIS!!!! Also, please reinstate the feature where we can sign up to be notified if/when more comments are made concerning the article(s) we've commented on so we can follow the conversation. Thank you.
Christa Bigue (Editor) June 10, 2013 at 01:50 pm
Thanks Sam! You should also post this Half Moon Bay (halfmoonbay.patch.com) and Pacifica PatchRead More (pacifica.patch.com)! I'm sure our readers would appreciate the great tip!
Michael Williams June 9, 2013 at 04:12 pm
Strongly suggest Patch readers check all the YELP reviews of this business. Very uneven experiencesRead More reported.
don torre June 4, 2013 at 06:55 am
what do the local Belmont restaurants think of this? do these people pay a license to the city?
Joan S. Dentler (Editor) June 4, 2013 at 07:15 am
Hi Don....thanks for your question. Yes, Off the Grid does pay a licensing fee to the city, and soRead More far, we haven't heard any concerns by local restaurants. The food trucks provide an option to a traditional restaurant---pick up and go----and they are only around 4-5 hours per week (on Mondays, typically not a big restaurant night anyway). Have you tried the food yet?